This LHD Loader RFQ Checklist helps you turn a request for a machine price into a procurement brief a manufacturer can assess. Send the intended duty, site constraints, evidence behind your measurements and the scope you want priced. Separate confirmed requirements from estimates. That gives the supplier a basis for proposing a configuration and gives your team a record against which to review the quotation.
You don't need every answer before making contact. You do need to make the gaps visible. This article sits within our underground loader selection guides and focuses on preparing the enquiry, rather than calculating a final machine selection.
Start with the job, then identify a candidate model
Describe what the loader will move, where it will collect the material and where it will discharge. State whether you're replacing an existing loader, opening a new heading or supporting a different loading arrangement. Attach the current machine's configuration sheet if it is a useful reference, but explain what must change.
A model number can be a starting point. The official ZONGDA ZDL204DD product page lists a 2 m³ bucket. Use that as a catalogue reference, not confirmation that the offered bucket and machine are suitable for your material. Ask the supplier to identify the exact configuration in its response.
If you haven't chosen a model, send the duty brief with your enquiry and browse the LHD product range for candidates. Avoid turning an early preference into a compulsory specification before the site review.
Label confirmed facts, assumptions and missing information
Give each requirement a status. A measured clearance, a planning estimate and an unanswered question shouldn't look identical in a quotation worksheet. Add the evidence, date and person responsible for closing any gap.
| Status | What to record | How the supplier should respond |
|---|---|---|
| Confirmed | A surveyed route drawing with a revision date | Assess the proposed machine against the attached revision |
| Assumed | A provisional material density used for planning | State how the assumption affects the proposal |
| Pending | Receiving hopper dimensions awaiting measurement | Identify the information needed before compatibility can be confirmed |
Keep a separate list of decisions still required from your mine team. If an assumption changes, issue an updated RFQ to every supplier being compared. Retain the earlier revision so a price change can be traced to a change in scope.
Package the technical inputs without burying the constraints
Use a short summary and clearly named attachments. Put the limiting conditions first: the narrowest access, unusual material characteristics, operating environment and any mandatory site requirements. Do not ask the supplier to infer them from a large collection of photographs.
- Material and duty: material description, measured or assumed loose density, fragmentation, moisture, desired production and planned shifts.
- Route: minimum surveyed width and height, bends, grades, floor condition, travel distance and discharge arrangement.
- Environment: altitude, temperature range, ventilation information, fuel specification and applicable mine requirements.
- Receiving equipment: truck or hopper identification, dimensional drawing, loading position and clearance constraints.
- Evidence: labelled photographs, drawing revisions and the person who can answer technical questions.
For the underlying capacity questions, use the payload and bucket volume guide. For access information, follow the loader route clearance checklist. Include the resulting inputs in the RFQ instead of relying on a general statement that the mine has enough space.
Ask for the proposed configuration and its exceptions
Require a response against each mandatory item. Ask the supplier to mark it as offered, offered with a qualification, excluded or awaiting clarification. A blank cell should remain an open question; don't read silence as agreement.
Request the proposed bucket, power unit, transmission, axles, tires, braking arrangement, operator protection and any requested optional equipment. Ask which items are standard and which change the quotation. Record the document revision governing the offer.
The ZDL307 technical specification records a 7 t rated load and a 3 m³ bucket. It also sets out operating restrictions, including exclusion of environments with flammable or explosive gases or coal dust. Those values describe that reference document. Current availability, configuration and suitability still require confirmation; see the ZDL307 technical reference page before citing it in an enquiry.
As an external example of specification detail, Caterpillar's official R1700 specifications list bucket variants separately from turning dimensions. The practical lesson is to request the chosen attachment and geometry explicitly. That source does not establish equivalence with any ZONGDA model.
Make the commercial scope comparable
Ask for the machine, options, initial parts, documentation and any requested support to be itemised. State the delivery destination and ask the supplier to define the delivery basis, named place, currency, validity period and exclusions. Keep production readiness and transport estimates separate.
A lower total can reflect a different scope. One offer may include a parts package while another leaves it unpriced. Use a comparison sheet with columns for requirement, offered specification, inclusion status, quoted amount and unresolved question. Don't rank incomplete offers solely by their headline totals.
For support, request the proposed commissioning, training, warranty and service arrangements in writing. Ask who performs each activity, where it happens and what is excluded. Treat these as matters to agree, not services automatically included with every machine.
Copy this RFQ template into your enquiry
Replace the bracketed fields and delete anything irrelevant. Mark unknowns as pending rather than inventing a value.
Subject: LHD loader quotation request — [project reference and destination]
Project: We require [quantity] loader(s) for [loading and transport task]. This is [replacement/new capacity]. Our target purchasing decision is [date]; required delivery timing is [target, subject to confirmation].
Duty: Material is [description]. Loose density is [value and units; measured/assumed]. Fragmentation and moisture are [details]. Planned operating schedule and production objective are [details].
Site: Attached route revision [identifier] shows access, bends, slopes and discharge position. Environmental conditions and mandatory mine requirements are [details]. Unverified inputs are [list].
Machine: Candidate model is [model or supplier recommendation requested]. Please specify the bucket and complete offered configuration, supported limits, options and exceptions.
Scope: Please itemise the machine, requested options, initial parts, documentation and proposed support. State delivery basis, named place, currency, validity, exclusions and schedule assumptions.
Response: Return a marked requirements sheet, relevant drawings and outstanding questions. Technical contact is [name and contact]. Purchasing contact is [name and contact].
Close the information gaps before accepting an offer
Review technical deviations before negotiating the final scope. Ask for revised documents when the supplier changes a component or attachment. Make sure the commercial quotation and technical schedule refer to the same configuration.
Bring maintenance into the review while the offer is still being defined. The LHD loader spare parts checklist helps structure the parts and documentation request. Keep optional stock recommendations separate from the parts actually included in the price.
Once the brief is ready, send your loader requirements to ZONGDA. Include an attachment list and identify the unresolved questions you want addressed first.
RFQ questions buyers often ask
Can I request a quotation without a route survey?
Yes, but identify the missing survey and request a preliminary response. Keep access suitability unresolved until the necessary measurements and configuration drawings have been reviewed.
Should every supplier quote the same model size?
Give suppliers the same duty requirements. If alternatives are welcome, ask for them separately, with the reasons for the change and its effect on the quoted scope.
Does a published specification confirm the machine I will receive?
No. Use it to frame questions. The final purchase documentation should identify the agreed configuration, applicable drawings, exclusions and any remaining conditions.
Next, distinguish LHD cycle time from a production promise.
Equipment to review
Reference model information and original technical sources are linked on the equipment pages. Confirm the proposed configuration and site requirements before purchase.