LHD loader cycle time explained through bucket filling, loaded travel, dumping, return travel and waiting time, with a distinction between cycle observations and production estimates.

LHD loader cycle time is the elapsed time for a loader to take up a load, carry it to a discharge point, empty the bucket and return to the loading position. Production also depends on the number of loaders that can work effectively. Where there is only one loading point, dispatch, equipment capacity, delays and equipment availability must be considered.

Bucket Filling in the Loading Cycle

The ZDL307 reference specification lists a rated load of 7 t and a stacking bucket volume of 3 m³.

The bucket filling time is included in the loader cycle time.

Bucket fill factor for LHD depends on the bucket shape, the material type/muck pile characteristics and the operator's skill and experience. Muck piles that contain larger rocks with voids between the rocks will have a lower fill factor and take longer to fill than a muck pile with a finer and more uniform material gradation.

Material Characteristics and Bucket Load

Material density, particle size and shape affect the bucket fill factor. In sticky materials such as clay, the bucket may not empty completely, thereby reducing the effective bucket capacity.

Wet and muddy loading conditions can affect the loading operation by making it difficult for the operator to see the muck pile and the truck body.

The work cycle of a loader consists of a number of segments. The mucking cycle consists of:

  • Loading, bucket filling
  • travelling with a full bucket
  • discharging, bucket emptying, and
  • returning empty to the loading position.

Cycle times depend on the type of loader, the nature of the material, the hauling distance and road conditions, the operator's skill and the loading and discharge conditions.

Loaded Travel Time

The haul route can have a major effect on production.

Speed depends on the weight (load and empty), gradient and the rolling resistance of the road.

The rolling resistance depends on the road surface.

Traction is limited by the coefficient of friction between tyres and road.

Turning and Positioning

At the muck pile, the loader has to be positioned to start loading and at the discharge point it has to be positioned to dump. Positioning is included in the cycle time.

Cycle time = loading time + travel time loaded + dumping time + travel time empty + positioning and turning times + wait times for other equipment.

The times for each part of the cycle are determined by the method of loading, the machine performance, the distance and conditions of the haul route, and the ability of the operator.

Dumping and the Receiving Equipment

At the discharge point the load is dumped either into an ore pass, truck or a stockpile.

Dumping into a truck is essentially a manoeuvring operation to place bucket over the truck body. Discharge into an ore pass can be a matter of simply moving to the edge of the pass and dumping the bucket. The discharge point may be the surface stockpile.

If the truck has to wait for the loader, or the loader has to wait for the truck, additional time is added to the cycle.

To reduce the total cycle time, the loader operator should be able to position and manoeuvre smoothly and quickly. A good road surface with adequate width helps positioning.

Waiting Time and Interruptions

Delays increase the total cycle time and reduce production.

If the loader has to wait at the dump point for a truck to spot, then this time is added to the total cycle time. To reduce waiting times there should be an adequate number of trucks to ensure that the loader does not have to wait.

Equipment should be matched according to the required production.

In general, whenever cycle time is estimated, the actual operating conditions should be used.

With multiple loading units, production can increase as long as the units do not interfere with each other.

The rate of production depends on the number of loaders that can be used effectively at the loading point and their capacity.

If loading from a single muckpile, where there is only one loading position, the loaders will interfere with each other. If there are multiple headings, loaders can be dispatched to different headings to avoid waiting.

It is preferable when the headings are separated and each loader can access the muck pile without interference.

With multiple heads, one loader can operate at the face while another is loading from another muck pile. The loaders will interfere if the road is too narrow for them to pass each other.

Recording a Complete LHD Cycle

To estimate the cycle time accurately, a time study should be conducted using representative loads and haul routes.

The measurements should cover all the elements in the cycle and include the operator delays.

  • time for bucket loading
  • time travelling loaded
  • time for manoeuvring at the discharge point
  • time for dumping
  • time for returning empty
  • time to manoeuvre at the muck pile and the delays.

Use the average times observed from a representative number of cycles. The data should be from cycles that are typical of the loading operation.

Cycle times should be measured for the different operator skills, road conditions and the nature of the material.

Once the cycle time for typical conditions has been obtained it can be used as a basis for estimating production. The cycle time should be adjusted for any changes in the conditions.

For example, an increase in haulage distance increases the total cycle time.

To calculate production, the loader's cycle time is converted into a rate. Production rates are usually expressed in tonnes per hour.

An availability factor can be applied to estimate the annual production.

Cycle Time and Production Estimates

Production depends on the loader capacity and the cycle time.

The loader specifications provide the bucket capacity and rated loads.

In practice the payload will vary with the material type, muck pile and operator technique.

Calculating the output requires that the loader cycle time be accurately measured.

Where the loader is loading trucks, the overall system must be balanced to achieve the desired output. In this case production limits are determined by the trucks and the loader.

If a single loader is loading into trucks the time taken to load a truck depends on the size of the truck relative to the loader. If there is insufficient truck capacity the loader will be idle and production lost.

If too many trucks are allocated to a loader, the trucks will have to wait at the loading point and this adds to truck cycle time and increases the cost of truck haulage.

LHD selection guides · LHD loader RFQ checklist · Request a configuration review

Technical references

Equipment to review

Reference model information and original technical sources are linked on the equipment pages. Confirm the proposed configuration and site requirements before purchase.

SPECIFY YOUR REQUIREMENT

Bring the operating conditions.
Request the right configuration.

Include loading duty, route clearance, truck interface, quantity and delivery destination in your inquiry.

Request a Technical Quote